The Version Report shows your team's progress towards completion of a version. The Version Report also shows you the predicted Release Date, based on your team's average rate of progress (velocity) since the start of the version, and the estimated amount of work remaining.
This page only applies to Scrum boards.
To view the Version Report,
Screenshot: Version Report (click to enlarge)
The horizontal axis starts on the version's Start Date; or if no Start Date is specified, the date on which an issue was first added to the version. The graph shows the state your version was in at any given point in time, in terms of your total and completed Story Points (or other Estimation Statistic of your choice), so that you can see how the scope may have changed, and how you are progressing towards completion of the estimated work.
The graph shows you the following predictions:
Note that 10% of the estimated work for the version will need to be complete before the predictions can be calculated.