This page only applies to Scrum boards.
The Epic Report is available in GreenHopper 6.1.2 and later versions.
The Epic Report shows a list of complete, incomplete and unestimated issues in an epic. It is particularly useful for planning work for an epic that may extend over multiple sprints.
Use the Epic Report to understand the progress towards completing an epic over time, and to track the amount of remaining work that's incomplete or unestimated.
To view the Epic Report,
Click View <Epic Name> in Issue Navigator to jump to the Issue Navigator and see a list of all the epic's issues.
Related pages:
Screenshot: Epic Report (click to enlarge)
Please note that the graph will look different if you are using Issue Count as your Estimation Statistic (rather than Story Points, as shown in this screenshot).