Once you have identified that an issue is due to be actioned, you will need to add it to a sprint. You can either add an issue to a future sprint, or to the sprint that is currently in progress (the active sprint).
Please note:
This page only applies to Scrum boards.
A planned sprint is a sprint which has not yet started (i.e. it is not currently visible in Work mode). A planned sprint is the collection of issues sitting above the sprint footer when you view your board in Plan mode.
To add an issue to a planned sprint,
Sometimes you may need to add an issue to the active sprint — that is, the sprint which is currently in progress (ie. the sprint which is currently visible in Work mode).
To add an issue to the active sprint,
Note that adding an issue to an active sprint will be shown as a 'scope change' event on the Burndown Chart for that sprint.
Screenshot: adding an issue to the active sprint