Problem
Unable to migrate JIRA from old 5.X JIRA to newer JIRA 6.x version
- Duplicated issue key can be observe in logs
The following appears in the atlassian-jira.log
localhost-startStop-1 ERROR [atlassian.jira.upgrade.UpgradeManagerImpl] Exception thrown during upgrade: Could not create index: SQL Exception while executing the following:
CREATE UNIQUE INDEX issue_proj_num ON public.jiraissue (issuenum, PROJECT)
Error was: org.postgresql.util.PSQLException: ERROR: could not create unique index "issue_proj_num"
Detail: Key (issuenum, project)=(0, 10251) is duplicated.
java.lang.RuntimeException: Could not create index: SQL Exception while executing the following:
CREATE UNIQUE INDEX issue_proj_num ON public.jiraissue (issuenum, PROJECT)
Error was: org.postgresql.util.PSQLException: ERROR: could not create unique index "issue_proj_num"
Detail: Key (issuenum, project)=(0, 10251) is duplicated.
at com.atlassian.jira.upgrade.tasks.UpgradeTask_Build6132.createIndex(UpgradeTask_Build6132.java:64)
at com.atlassian.jira.upgrade.tasks.UpgradeTask_Build6132.doUpgrade(UpgradeTask_Build6132.java:54)
at com.atlassian.jira.upgrade.UpgradeManagerImpl.doUpgradeTaskSuccess(UpgradeManagerImpl.java:814)
at com.atlassian.jira.upgrade.UpgradeManagerImpl.runUpgradeTasks(UpgradeManagerImpl.java:681)
at com.atlassian.jira.upgrade.UpgradeManagerImpl.doUpgrade(UpgradeManagerImpl.java:540)
at com.atlassian.jira.upgrade.UpgradeManagerImpl.doUpgradeIfNeeded(UpgradeManagerImpl.java:475)
at com.atlassian.jira.upgrade.UpgradeManagerImpl.doUpgradeIfNeededAndAllowed(UpgradeManagerImpl.java:410)
at com.atlassian.jira.upgrade.UpgradeLauncher.checkIfUpgradeNeeded(UpgradeLauncher.java:107)
at com.atlassian.jira.upgrade.UpgradeLauncher.start(UpgradeLauncher.java:55)
at com.atlassian.jira.startup.ActiveServicesLauncher.start(ActiveServicesLauncher.java:49)
at com.atlassian.jira.startup.DefaultJiraLauncher$3.run(DefaultJiraLauncher.java:140)
at com.atlassian.jira.config.database.DatabaseConfigurationManagerImpl.doNowOrEnqueue(DatabaseConfigurationManagerImpl.java:345)
at com.atlassian.jira.config.database.DatabaseConfigurationManagerImpl.doNowOrWhenDatabaseActivated(DatabaseConfigurationManagerImpl.java:215)
at com.atlassian.jira.startup.DefaultJiraLauncher.postDbLaunch(DefaultJiraLauncher.java:124)
at com.atlassian.jira.startup.DefaultJiraLauncher.access$100(DefaultJiraLauncher.java:33)
at com.atlassian.jira.startup.DefaultJiraLauncher$1.run(DefaultJiraLauncher.java:86)
at com.atlassian.jira.util.devspeed.JiraDevSpeedTimer.run(JiraDevSpeedTimer.java:34)
at com.atlassian.jira.startup.DefaultJiraLauncher.start(DefaultJiraLauncher.java:81)
at com.atlassian.jira.startup.LauncherContextListener.contextInitialized(LauncherContextListener.java:72) <+5> (StandardContext.java:4992) (StandardContext.java:5490) (LifecycleBase.java:150) (ContainerBase.java:1575) (ContainerBase.java:1565)
at java.util.concurrent.FutureTask.run(FutureTask.java:266)
at java.util.concurrent.ThreadPoolExecutor.runWorker(ThreadPoolExecutor.java:1142)
at java.util.concurrent.ThreadPoolExecutor$Worker.run(ThreadPoolExecutor.java:617)
at java.lang.Thread.run(Thread.java:745)
Cause
This is due to previous JIRA 5.x version is having different column in jiraissue table.
- Issue key and project key is stored in one column
- Where as in newer JIRA, issue key (issuenum) and project key(project) is seperated
Environment
- Perform the following SQL to verify once you have restore the old instance to the new instance, if there is value returned , then proceed to the solution
select issuenum, project from jiraissue group by issuenum, project having count(*) > 1;
Resolution
Perform the following SQL update to update the issue number accordingly
- Proceed to restore to the latest intended JIRA version
Run the following SQL for all the returned query
UPDATE jiraissue SET issuenum = (SELECT pcounter+1 FROM project WHERE id = 'YYYY') WHERE id = (SELECT max(id) FROM jiraissue WHERE project = 'YYYY' AND issuenum = 'xxxx'); UPDATE project SET pcounter = pcounter+1 WHERE id = 'YYYY';
subtitute XXXX with the issuenum that is return from
select issuenum, project from jiraissue group by issuenum, project having count(*) > 1;
and YYYY from the project
Run the update until query return null
Scripting may be needed if large amount of data need to be altered to generate the update SQL